As part of the Sarfas Pigging EPC (Engineering, Procurement, and Construction) project for PT Pertamina Energy Terminal, our main scope of work focuses on detailed engineering design (DED) and construction of the Compressor Station.
Our responsibilities cover all technical aspects, from structural analysis and simulation for the compressor shelter to the design of precision foundations and floors. The foundation design is based on soil investigation data (sondir) that we conducted on site to ensure optimal bearing capacity. We also compiled complete technical specifications for materials (K-350 concrete for foundations, reinforcing steel, and steel profiles) and designed a three-coat painting protection system for shelters and pipe supports.
Sector
Oil & Gas / Energy Terminal.